[7.01.2009]
Waste treatment department obtained complete satisfaction implementing works in December last year
Waste treatment department of the company completed the last successfully. In the report month the department succeeded in treating by means of mechanical treatment plants 980 thousand m3 of waste water in site N 9 (Baku Oil Refinery named after Haydar Aliyev) and 920 thousand m3 in site N 7 (Azerneftyagh).
Accumulated 328 tons of oil slope in tanks in site N 7 has been completely treated by means of Alfa Laval Plant, 9 m3 of wax (paraffin) has been treated in wax treatment site.
Alongside with it, in order to provide operation longevity of all active plants there was carried out a range of fixing works in place in December month.
In order to put in operation new Facet Waste Water Treatment Plant there was replaced and recovered a pump N 3 in Flotation Pump House, as well as assistant pumps of both Alfa Laval Plants have been refreshed.
Last year the department also succeeded in providing some preparation works in site, like spilling in heat changers were prevented, pipelines isolated, electricity systems were refreshed new electro-devices were installed in sites, there was carried out concreting works in receiving tank pump house of site N 7, 500 mm inlet line of 1-3 pumps pits were renewed and new line was put for oily products treatment.
Provision of safety of personnel and improving work condition are not out of attention as there have been implemented a range of activities.
|
|