[8.10.2009]
Electro mechanical repair department has carried out
required preparation efforts for winter season
There have been carried a range of required preparation works for winter season 2009-2010 years.
According to measurements plan there has been laid a steam pipeline 114x4 mm diameter, 294 meters of length that was taken from magisterial pipeline existing in operational site 9 of Baku Oil Refinery named after Haydar Aliyev. This pipeline was constructed for oil sludge processing and pigging wax treatment plants in operational sites of the company.
A new constructed boiler house has also been supplied with two water pipelines 57 mm, 245 meters of length and 89x4 mm, 45 meters of length.
For service provision of the boiler house equipments there built an operating room supplied with any required electrical equipments.
Electro mechanical repair department is continuously providing a range of needed activities for non-stop work regime.
|
|